A00 

Location: 19191 Vallco Parkway APN: 316-20-117

Applicant: Apple, Inc.

Property Owner: Apple, Inc.

Architect: STUDIOS Architecture

City Contact: Gian Paolo Martire, gianm@cupertino.org

Tentative Public Hearing Dates:

Planning Commission: March 28, 2023

City Council: April 13, 2023

Application Summary:

Development and Architectural and Site Permits for the redevelopment of an approximate 8 acre site that consists of demolishing an existing 141,024 square foot office building and replacing it with a four story 282,320 square foot building (280,020 square feet of office & 2,300 square feet of commercial), a detached parking structure and associated site improvements; A Tree Removal Permit to allow the removal and replacement of 113 trees.

CEQA

CEQA Guidelines Section 15183 Checklist and memo has been prepared. Guidelines Section 15183, Projects Consistent with a Community Plan or Zoning, provides a special streamlining process that exempts qualifying projects from additional analysis if the project is consistent with development density established by existing zoning, community plan, or general plan policies for which an Environmental Impact Report (EIR) was certified.  

Project Data:

Lot Size: 7.9 acres

Type: Office Development

Land Use: Commercial / Office/ Residential

Zoning: P(MP,CG)

Permits Required:

Permit approvals including, but not limited to the following, may be required:

  • Development Permit (DP-2021-001)
  • Architectural and Site Approval (ASA-2021-003)
  • Tree Removal Permit (TR-2021-020)
Development Standards
SITE PLAN & RENDERINGS